Improvement of the Calculation Standard for Prolongation cost of Long-term Continuing Contracts Construction Project
Recommendations
Search

장기계속계약공사의 공기연장 추가간접비 산정 개선방안

논문 기본 정보

Type
Academic journal
Author
Jeong, Kichang (한국건설관리연구원) Lee, Jaeseob (Korea Institute of Construction Management)
Journal
한국건설관리학회 한국건설관리학회논문집 한국건설관리학회논문집 제18권 제2호 KCI Accredited Journals
Published
2017.1
Pages
30 - 37 (8page)

Usage

cover
Improvement of the Calculation Standard for Prolongation cost of Long-term Continuing Contracts Construction Project
Ask AI
Recommendations
Search

Research history (5)

  • Are you curious about the follow-up research of this article?
  • You can check more advanced research results through related academic papers or academic presentations.
  • Check the research history of this article

Abstract· Keywords

Report Errors
In Korea, additional indirect costs generated from the time period extension of public construction projects have been studied. Practical claims against such costs are increasing. There are no clear criteria for calculating the delay cost caused by the extension, and thus calculation methods differ across entities. Logical valid calculation methods have also not been researched. Further, there are no Korean studies on the additional indirect cost caused by a suspension in a public construction project on a long-term continuing contract. The purpose of this research is to propose a method of calculating the indirect cost incurred by construction time extension that reflects the characteristics of Korean public construction projects. The cost patterns generated during construction periods were analyzed, and then the current criteria of calculating the indirect costs caused by the extension were examined. Following this, actual conditions and practices in the field were surveyed and the current calculation method was applied to a model case to compare the actual cost and that determined from the current calculation method. Issues with the current method were identified by this comparison. Based on this, this research proposes a method of calculating the total actual cost caused by a suspension in a public construction project that is appropriate for calculating the additional indirect cost generated by a suspension in a public construction project on a long-term continuing contract.

Contents

No content found

References (12)

Add References

Recommendations

It is an article recommended by DBpia according to the article similarity. Check out the related articles!

Related Authors

Recently viewed articles

Comments(0)

0

Write first comments.